Instructions for Applying for a Street Use ROW Construction New/Replace Concrete Driveway Permit
Follow these steps to apply for a Street Use concrete curb cut or driveway permit using the Seattle Services Portal. This process helps ensure that your application for curb cut or driveway work impacts to the public meets Street Use's requirements for uses of the right-of-way (ROW) with minimal impacts to the traveling public and existing infrastructure.
What You Need to Know about Curb Cut or Driveway Permits
Concrete curb cut/driveway work is permitted under the Street Use ROW Construction record type using the use type of New/Replace Concrete Driveway.
For stand-alone concrete curb cut/driveway work:
- The Street Use permit covers concrete curb cut/driveway work both in the right-of-way and on private property.
- The Seattle Department of Construction and Inspections (SDCI) reviews their portion of the work under the Street Use permit.
For concrete curb cut/driveway work that is covered by an SDCI Construction permit:
- The Street Use permit covers concrete curb cut/driveway work only in the right-of-way.
- The Street Use permit cannot be issued until the SDCI Construction permit is issued.
If an SDCI stand-alone curb cut permit exists prior to November 12th, 2020:
- The applicant still receives two permits, one from each department.
- The SDCI review is completed as part of the SDCI Construction (CN) permit.
- The SDOT ROW Construction permit is required, but it is not routed to SDCI for curb cut review.
- Relevant fees are collected by each department separately.
What You'll Need to Start Your Application
Before you start, gather these documents. Most are available on the Street Use Permitting Checklists, Forms, and Templates page.
- Letter of Authorization: A signed document that gives permission from the property owner to another party (like the Applicant) to manage the permit or pay the fees (like the Financially Responsible Party).
- ROW Impact Plan: A ROW Impact Plan (ROWIP) shows all temporary construction-related uses in the right-of-way. We use the ROWIP to understand how the right-of-way will function during construction and identify safety, mobility, access, and construction conflict issues that need to be addressed.
- Site Plan (for many ROW Construction permits): A site plan is a plan view drawing or an illustration of a site as if looking straight down from above. A site plan shows the project site, proposed installations, and existing conditions in relation to each other. We use the site plan to understand the proposed location, what is being constructed and how the proposed installations may affect use of the ROW.
- SDCI Site Plan (for New/Replace Concrete Driveway permits): A site plan is an accurate drawing or map of a property that shows its size and shape; and the size, shape and location of man-made and natural features (such as buildings, structures, driveways, and trees) on the property. Site plans show both what currently exists on the site and what physical changes you wish to make to the site.
- Any additional documents specific to your project. A reviewer will notify you if additional materials are needed.
Step-by-Step Guide
Step 1: Log in or Register
- Go to the Seattle Services Portal.
- Log in:
- If you already have an account, log in with your credentials.
- If you don’t have an account, register for a new account before proceeding.
Step 2: Start Your Application
- Click the Home tab.
- Under Create New, click Permits – Street Use.
- Records are grouped by type of permit. For a New/Replace Concrete Driveway permit, click the triangle symbol to expand the ROW Construction group.
- Click ROW Construction Permit.
Step 3: Provide Your Project Location
- On the Location Information page, enter your project address. For best results, only enter the Street No. and Street Name when searching.
- Street No. (required): Enter the house or building number.
- Street Name (required): Enter the name of the road. For a numbered street, such as 700 5th Ave, only enter "5".
- Click Search. If prompted, select the correct address or parcel number and click Select.
- Click Continue to proceed.
Step 4: Provide Contact Information
On the Contacts page, provide contact details for:
- Applicant: You, the person filling out this application.
- Owner: The company or contractor performing the work.
- Financially Responsible Party (FRP): The person or organization in charge of paying any permit fees.
- Onsite Contact: The person available if we need to speak with somebody onsite.
- Optionally, add additional contacts like an Authorized Agent in the Additional Contacts section.
-
To add a contact:
- Click Myself to auto-populate the contact information from your Seattle Services Portal user account.
- Click Someone Else to find an existing contact. If the person or organization isn’t found, click the “Person or organization not listed? Add them here." link.
Note: If the Applicant or Financially Responsible Party is different from the Owner, a Letter of Authorization will be required later.
- Click Continue to proceed.
Step 5: Provide Your Project Details
- Optionally enter a Project Name for your reference. The project name will appear on your invoice if you are billed.
- For the Project and Location Description, enter a detailed description. The screen displays some guidance about the kind of information to provide.
- Click Continue to proceed.
Step 6: Provide Related Information
- Optionally use this section to tell us about what else is related to your application:
- Add any relevant Seattle Department of Construction and Inspection (SDCI) or Seattle Department of Transportation (SDOT) Street Use permit numbers.
- Optionally, enter a Customer Reference. There are two fields you may use for your reference. Customer Reference appears on your invoice, if you are billed.
- Optionally, enter Estimated Project Duration that indicates how long the overall project will take.
- Optionally, update the 24-Hour Contact and Restoration Party information.
- Click Continue to proceed.
Step 7: Provide Project Use Information
- On the Use Information page, scroll down and click Add a Row.
- A pop-up window prompts you to provide project information. Fill in the fields. Required fields are marked with a red asterisk. Click on a blue circle with a question mark for help.
- Use Type (required) – Select New/Replace Concrete Driveway from the dropdown.
- Space (required) – Defaults to A. The Space is an informational designation for an area in the right of way. You may leave the default value. Note: If you add another use row for the same Use Type, then optionally update Space to B, and so on.
- Rate Start Day (required) – Defaults to 1. You may leave the default value.
- Use Start Date (required) – Select the start date for your Use.
- Duration (Calendar Days) (required) – Enter the number of elapsed calendar days for your Use.
- Exp Date (read only) – Auto populates based on Use Start Date and Duration. Note: If you tab out of the field, depending on your browser, the calculated date may not appear until the final review step before you submit your application.
- Total Days in ROW (required) – Enter the total number of actual days that you will occupy the right of way. This value must be greater than zero and less than or equal to Duration.
- Side of Street (required) – Select side of street where work will be performed. For road closures, pick Both Sides. If the work will be on more than one street frontage, you will be able to create another use row later in the process.
- Work Days (required) – Defaults to Every Day. Select from dropdown if not every day. Options are Weekdays Only (Monday through Friday), Weekends Only (full weekend), Every Day (seven days a week), or Partial Week (not all weekdays or not all weekend or a combination that is not included in the above options).
- Use Area (required) – Enter the right-of-way area for the use, in square feet.
- Sidewalk Impact (required) - Concrete sidewalk or asphalt pathway. Defaults to None. If your work will block the sidewalk, select a value from the dropdown.
- Bike Lane Impact (required) – 24/7 dedicated bike lane. Defaults to None. If your work will block the bike lane, select a value from the dropdown.
- Travel Lane(s) Impact (required) – General purpose travel lanes. Defaults to None. If your work will block the travel lane(s), select a value from the dropdown.
- Transit Lane Impact (required) – 24 hour dedicated bus or other transit lanes. Defaults to None. If your work will block the transit lane, select a value from the dropdown.
- Parking Lane Impact (required) – Paid or unpaid parking lanes or spaces. Defaults to None. If your work will block the parking lane, select a value from the dropdown.
- Other ROW Impact (required) – Alley, gravel shoulder, planting strip, etc. Defaults to No. If your work will block other right of way, select Yes.
- Click Submit.
- The pop-up form closes, and you are returned to the Use Details section. The project information you just added is visible.
- To add additional project information, repeat the steps.
- Once all project information has been added, click Continue to proceed.
Step 8: Provide Curb Cut Information
The Curb Cut Information section is used for SDCI’s review and to populate SDCI’s curb cut fee on SDOT’s permit.
- Fill in all the fields.
- Click Continue to proceed.
Step 9: Attach Required Documents
Some documents are required at application submission, and some may be required later during the review process.
- To upload a document, click Select under the Upload Documents section.
- Select your document:
- Click Select in the File Upload popup.
- Select your document and click Open.
- Click Done in the File Upload popup.
- Select your document type:
- In the Document Type dropdown, select the document type that matches the document you uploaded. For example, select "Site Plan" as your document type when uploading the matching document.
- Optionally, enter the Description of the document.
- Click Save and wait for the upload to complete. Note: It may take a few minutes for your document to fully upload.
- Repeat steps for each additional document required. When prompted, select the document type that matches the document you are uploading.
- Click Continue to proceed.
- If you see a red Attention message, that means you either have not selected the correct Document Type, and/or have missed a required document.
- If a document is missing, go back to step 1 in this section and upload the missing document.
- If you selected the wrong Document Type on a document that you have already saved, upload the document again and pick the Document Type that matches the Condition in the Attention message. You may also add a description explaining that you are uploading the document a second time with the correct Document Type.
Step 10: Review and Submit
- On the Review page:
- Verify that all information is correct.
- Make edits as needed by clicking Edit in the relevant sections.
- Scroll to the bottom. Agree to the certification statement by checking the box.
- Click Continue to submit.
Step 11: Confirmation Displays
A message displays confirming that your application is submitted for review.
- Your record number has a format of SUCONST0000000.
- Keep a record of your Record Number.
An e-mail is sent to the four required contacts on the application notifying them of the application submission.
You can log into the Seattle Services Portal at any time to view the status of your application.
Congratulations! Your application has been submitted for review. The Street Use team will contact you if additional information is required. For questions or updates, email SDOTPermits@seattle.gov and include your Record Number in the subject line.
You can log into the Seattle Services Portal at any time to track the status of your application.
Need Help?
Visit the Seattle Services Portal help center, email SDOTPermits@seattle.gov, or call (206) 684-5253.